Balance Spent
Routine summer maintenance $7,000.00 -$1,213.08 $8,213.08
7/22 hand clearing signs-$548.70
7/27 grade end of road -$597.12
9/26 grade -$1,442.80
6/6 grade end RSA -$298.56
6/30 30 hrs machine clear -$5,325.90
Misc repairs and upgrades $10,000.00 $544.73 $9,455.27
7/19 gravel to corners -$4,192.80
7/22 asphalt patch -$5,079.57
1/24 remove tree in road -$182.90
Snowplowing $15,000.00 -$3,575.48 $18,575.48
12/6 truck plow -$1,199.91
12/30 truck plow -$1,199.91
1/3 grader -$3,489.45
1/6 truck plow -$1,199.91
1/16 truck plow -$1,199.91
1/17 truck EFR -$906.78
1/30 truck plow -$1,199.91
2/9 grader + hardpack for discount-$1,996.07
2/24 truck plow -$1,199.91
2/27 truck plow -$1,199.91
3/2 grader + cow pie -$3,783.81
Mailing supplies $100.00 $66.00 $34.00
stamps -$34.00
Total -$4,177.83 $36,277.83
Direct cost to borough $10,690.00 $10,690.00